Posted date
Sprint Operation Guide
Table of contents
- Overview
- Basic rules and premise
- Sources
- Overall sprint planning
- Points of caution for contract development
- Sprint execution
- Prerequisites
- Sprint workflow
- Sprint planning meeting
- Daily work
- Product backlog refinement
- Sprint review
- Sprint retrospective
- Troubleshooting
- Stories are not finished within sprints
- A task was found to be missing from the story
- Product managers
- Role
- Story splitting cheat sheet
- Criteria for good stories: INVEST
- Story splitting format
- Daily scrums
- Sprint retrospective
- Introduction
- Workflow of retrospective
- Points of caution when conducting retrospectives
- Retrospective assessment sheet
- Source
- Criteria for good tasks: SMART
- Specific
- Measurable
- Achievable
- Relevant
- Time-boxed
Troubleshooting
Stories are not finished within sprints
Since Scrum encourages teams to be autonomous, the velocity of the next sprints tends to decrease if the schedule is unrealistic. This is unavoidable in cases where the team is clearly not skilled enough, but if velocity is simply decreased every time this issue occurs, the productivity of the team will be lowered further than necessary.
Below are examples of points that can be reviewed to increase velocity in the next sprint.
- Are the end conditions of the story suitable?
- Is the team being distracted by individual work that is outside the set format?
- Is there any work (preparation of XX, etc.) that isn’t being designated as a task?
- Are too many impediments building up and creating too much of a psychological burden?
The product manager must take the initiative to write code to help the team, without hesitation. It is arguably more productive if the product manager is involved in pair programming rather than simply reviewing what others have created.
A task was found to be missing from the story
Team members should not decide by themselves that the work cannot be completed if that task is not done. The matter should be escalated to the product manager.
The following options are possible.
- Switch the tasks and implement the new task in this sprint.
- Add the task to the product backlog and execute it in a later sprint.
- The concern that the task is missing may be unfounded.